Construction of Sheikh Lutfar Rahman Bridge (Patgati Bridge) over the river Madhumati at 40th Km. of Pirojpur-Gopalgonj Road under Gopalgonj Road Division during the year 2009-2010.
Description of Works
Bridge Length=391.491m (2x48.095+2x48.52+2x48.61+1x101.035)
Width of the Bridge = 9.50m
Total Span = 7 Nos.
Navigation Clearance Height = 7.62m
Division-1: General and site facilities = Tk. 11,11,600/-
Division-2: Earth works = Tk. 1,53,23,978.40
Division-3: Pavement works = Tk. 2,06,96,977.50
Division-4: Foundations Works :
a. 1200mm dia pile quantity = 52 Nos., Pile length = 45, to 53m
b. 1000mm dia pile quantity = 92 Nos., Pile length = 29, to 38m
= Tk. 11,20,07,350.00
Division-5: Structure works :
a. PC Girder quantity = 30 Nos., Length 48.80
b. Lunching of Steel Truss (Supplied by RHD from China) length = 101.035m
c. Steel Truss height = 12m
= Tk: 23,68,06,062.24 (Excluding cost of Steel Truss)
Division-6: Incidental = Tk. 1,31,52,169.80